Siemens has placed multi-million pound contracts with companies across the UK for the construction of the transmission infrastructure for the Moray East Offshore Windfarm.

As the lead contractor for onshore transmission infrastructure construction works for the 950MW windfarm, Siemens has placed several subcontracts since work began in September 2018.
 
BAM Nuttall has been appointed as the main subcontractor to complete the civils work for the onshore substation that is being constructed to connect the project to the grid. The contract will see BAM Nuttall’s Glasgow office complete civil and building works, including foundations for the transformers, shunt reactors and switchgear equipment as well as constructing the internal road, fence and internal drainage works at the new onshore substation being built at New Deer.
 
Firms from the area local to the onshore construction sites have been working on site enabling works ahead of major civil construction works including preparation of the substation site and onshore cable route as well as provision of building materials and plant.
 
Perth civil engineering company, I & H Brown are undertaking enabling work on the onshore substation site, while JGC Engineering and Technical Services of Thurso will fabricate and fit out the high voltage equipment containers which will be shipped later this summer for integration into the project’s offshore substation platforms. In addition, Barrier Architectural has been appointed to fabricate a set of containers from its Stockton-on-Tees facility.
 
VolkerInfra, based in Preston, will provide and install the high voltage onshore export cables for the project which stretch the 35km underground cable route from near Whitehills on the Aberdeenshire coast to the new substation site south of New Deer.  It has appointed Scottish companies to deliver road improvements and complete horizontal directional drilling works required for the cable installation.
 
Siemens is responsible for the complete construction of the onshore substation, including three SVC Plus advanced STATCOMs, as well as supplying three offshore substation platform topsides for the project.